CDM 2015 for small contractors: the construction phase plan, the notification thresholds, and how project software keeps the record

4 November 2026 · 10 min read · By the AevoMind team

A translucent green glass house frame with stairs and a roof, standing on a flat glass plate edged in gold, standing for a building project resting on a written plan.

HSE says a construction phase plan is required for every construction project under CDM 2015, and projects over set thresholds must be notified to HSE. A job can cross the second threshold by total worker days without ever having 20 people on site. Software can keep the plan, the headcount and the inductions together for every job, but a competent person must identify the hazards and judge what has changed.

The short answer

Under the Construction (Design and Management) Regulations 2015, HSE says “a construction phase plan is required for every construction project”, however small. For a typical small job the plan can be short, but it must exist before the work starts, and larger jobs have an extra duty: notification to HSE once they pass set thresholds.

For a contractor with many jobs running at once, that is a record-keeping problem repeated on every site. A project system can hold a plan for each job, keep who is on site and who has been inducted, and warn when a job is heading towards the notification thresholds. It cannot decide what the hazards on a site are or whether the plan still fits the work. A competent person does that.

A short and a tall matte green block with a thin brushed-gold bar laid across the top of the taller one, standing for a threshold a project can cross.
A threshold that a job can cross by length, by headcount, or by total effort.

The plan that every job needs, and how short it can be

HSE’s leaflet for small builders, CIS80, is direct about the scale of it: “A simple plan before the work starts is usually enough to show that you have thought about health and safety.” It gives examples of small-scale routine work, including installing a kitchen or bathroom, roofing work and loft conversions, and lists what to write down:

Each of these is a field on a job. None of them is hard. The difficulty is that there is one set per site, they are needed before the work starts, and they change when the work does.

Who has to do what: client, principal contractor, contractor

CDM 2015 spreads the duties across the people on a project, and the HSE pages set out each role. The ones that create paperwork for a contractor are these:

With a domestic client, the principal contractor normally takes on the client duties as well. If no principal contractor is appointed, HSE says the contractor in control of the construction phase carries out that role. For a small firm, that can mean holding several sets of duties on one job.

A ring of glass tokens glowing green with three glowing gold tokens joined by thin lines of light to a point at the centre, standing for several contractors connecting to one plan.
On a job with several contractors, the plan is the point that every one of them connects to.

Notification: the thresholds a job can cross without anyone noticing

HSE defines a notifiable project as one “where planned construction work will last longer than 30 working days and involves more than 20 workers at any one time; or where the work exceeds 500 individual worker days”. For those, a commercial client must notify HSE in writing and “ensure a copy of the notification is displayed in the construction site office”. HSE’s page on how to notify points to the online F10 form.

There are two separate tests, and the second is the one that surprises people. A job does not need 20 people on site at once to cross it. Twelve workers for 45 working days is 540 worker days, which exceeds 500, and the project is notifiable even though there were never more than 12 people there. HSE’s leaflet adds that a job above those levels “is likely to be too complex for this simple plan format”.

That makes the planned headcount and duration worth recording at the quote stage, not after the job has grown. A scope change that adds labour can move a job across the line without anybody deciding that it should.

Why the plan is worth the effort

The HSE fatal injury statistics are a reminder of what the regulations are for. Construction recorded more worker deaths than any other single industry in 2025/26.

Construction recorded the most worker deaths of any industry in 2025/26: 25 of 126Fatal injuries to workers by main industry, Great Britain, 2025/26 (provisional)
Construction25
Agriculture, forestry and fishing22
Manufacturing18
Transportation and storage15
Wholesale, retail, motor repair, accommodation and food11
Admin and support services9
Waste and recycling6
All other industries19

Source: Health and Safety Executive, Work-related fatal injuries in Great Britain (RIDDOR). HSE says the 2025/26 figures are provisional and will be finalised in July 2027. One death with an unknown industry is not shown; the industries shown, plus that one, total 126. These are deaths across a whole industry, not only on projects covered by CDM 2015.

Show the data
Fatal injuries
Construction25
Agriculture, forestry and fishing22
Manufacturing18
Transportation and storage15
Wholesale, retail, motor repair, accommodation and food11
Admin and support services9
Waste and recycling6
All other industries19

These are provisional figures for a whole industry, not for projects covered by CDM 2015 specifically, and they say nothing about any single firm. In HSE’s figures for the same year, falls from a height were the most common kind of fatal accident across all industries, at 31 deaths. The leaflet’s first example of a danger to plan for is working at height, which it ties to the need for scaffolding.

A green document folder with a gold tab and a clear glass paperweight resting on top, standing for a complete job file kept ready to produce.
A closed job file, complete and ready to produce if it is asked for.

What software can do, and what it cannot

This is project-record work, repeated for every site. The chart below uses illustrative figures, not client data, for a contractor with about 25 live jobs.

The paperwork behind a contractor running about 25 live jobsIllustrative hours a month for a contractor with about 25 live jobs, by hand and with a system
By handWith a system
Writing or adapting a construction phase plan for each job12 hrs5 hrs
Collecting site inductions and who-is-on-site records10 hrs3 hrs
Checking each job against the notification thresholds4 hrs1 hrs
Chasing the client for asbestos, services and access information8 hrs4 hrs
Reviewing and revising plans when the work changes6 hrs4 hrs

Illustrative inputs, not client data. Totals: 40 hours a month by hand against 17 with a system. Reviewing and revising a plan falls least, on purpose: someone who knows the site decides what has changed and what it means. A system removes the retyping, collecting and threshold-checking, not the judgement. Substitute hours you have measured.

Show the data
By handWith a system
Writing or adapting a construction phase plan for each job12 hrs5 hrs
Collecting site inductions and who-is-on-site records10 hrs3 hrs
Checking each job against the notification thresholds4 hrs1 hrs
Chasing the client for asbestos, services and access information8 hrs4 hrs
Reviewing and revising plans when the work changes6 hrs4 hrs

The shape matters more than the figures: retyping a plan for each job, collecting inductions and checking thresholds is mechanical, while deciding what has changed on a site is not. A projects and delivery system with milestone planning, task boards and time tracked against budget can hold each job’s plan beside its programme. Used well, it can:

What it cannot do is identify the hazards on a particular site, decide whether a job is notifiable in a borderline case, or appoint a principal contractor. Those are decisions for a competent person. Our installer platform is built on one shared record per job, and the specifics are set in an assessment visit. For related admin, see field service software for installers and MCS installer job management.

A track of connected glass segments lit green up to a gold marker and dim beyond it, standing for a plan kept current as a project progresses.
A plan that is current at every stage, from the first day to the last.

Where to start this week

  1. Pick three live jobs and ask whether each has a written construction phase plan, dated before the work started.
  2. Check each job’s planned duration, peak headcount and total worker days against the two notification tests.
  3. Write one short plan template from the CIS80 headings, and use it for the next job.
  4. Check who holds the client information on services, access and asbestos, and when you get it.
  5. Test one job: could you show, today, who is on site, who has been inducted and who is responsible?

This is general information based on the HSE pages and leaflet as we read them on 4 November 2026. The HSE CDM pages carry no publication date, so check the current position. We have not covered the regulations themselves, HSE’s detailed guidance, the F10 form or penalties, and this is not legal advice.

Frequently asked questions

Does every construction job need a construction phase plan?

HSE says a construction phase plan is required for every construction project under CDM 2015, and that it does not need to be complicated. For small-scale routine work such as a kitchen or bathroom installation, roofing or a loft conversion, HSE's busy-builder leaflet says a simple plan before the work starts is usually enough to show that you have thought about health and safety. Larger or notifiable jobs are likely to be too complex for that simple format.

When does a construction project have to be notified to HSE?

HSE describes a notifiable project as one where the planned construction work will last longer than 30 working days and involves more than 20 workers at any one time, or where the work exceeds 500 individual worker days. For notifiable projects a commercial client must notify HSE in writing and make sure a copy of the notification is displayed in the construction site office. A job can meet the second test without ever having 20 people on site: 12 workers for 45 working days is 540 worker days.

Who has to prepare the construction phase plan?

HSE says the principal contractor must prepare a written construction phase plan before the construction phase begins, then implement it and regularly review and revise it. Where there is only one contractor, that contractor must ensure a plan is drawn up before setting up the site. A commercial client must ensure the plan is prepared before that phase begins. When working for a domestic client, the principal contractor or sole contractor normally takes on the client duties as well as their own.

What should a simple plan record?

HSE's busy-builder leaflet lists key dates, information from the client such as where services and isolation points are, access restrictions and any asbestos, who else is on site with their contact details, how you will communicate and what you will do if the plan or materials change, the main dangers and how they are controlled, welfare facilities, the person responsible for the job running safely, and how supervision is provided.

Do these rules apply in Northern Ireland?

The HSE pages say CDM 2015 came into force in Great Britain on 6 April 2015, and this article covers only the HSE guidance for Great Britain. We have not reviewed the arrangements in Northern Ireland, so check them separately if you work there.